The City of Salem is buzzing with momentum as several major improvement projects move forward—each one laying the foundation for a stronger, more vibrant community. These developments reflect our shared commitment to growth, functionality, and beautification, and signal a bright future for Salem residents and visitors alike.
One of the most visible signs of progress is in the heart of downtown, where the current phase of the long-anticipated Downtown Project is nearing completion. After months of steady effort, the new light poles are being installed. These poles will not only provide historic replica lighting that complements the district’s charm, but they’ll also allow for seasonal decorations, flags, and banners that will add even more life and color to Salem’s central hub. This milestone marks a significant achievement in a project that has been years in the making—and it’s just the beginning.
This month, the Downtown Project is wrapping up as the Maggi Construction crew finishes the sidewalk and drainage work on the corner in front of the Bank of Salem. We extend our sincere appreciation to all the businesses and building owners for their patience and understanding throughout the construction process. The next steps include the installation of the historic replica lights atop the new poles, followed by the selection of downtown furnishings such as trash receptacles. One exciting addition to the furnishings—graciously provided by the Dent County Health Center—is the set of bicycle racks that will be installed throughout downtown and in a few select locations. This cooperative effort is a great example of local collaboration and the shared benefits it brings to our community.
Next, attention will shift just a block away to the historic Dent County Courthouse Square, where Dent County will begin the next phase of revitalization. Planned upgrades will enhance both the beauty and functionality of this iconic public space, making it even more welcoming and accessible for community events, gatherings, and everyday use.
Tree trimming of one of the city’s electrical feeder lines is also currently underway and will continue through the end of this month. Crews are trimming trees and branches in accordance with Missouri State Statute, which requires that trees be trimmed or removed within 10 feet on each side of the electrical line to maintain safe clearance. Typically, crews spend one to two days trimming, followed by a return visit to clean up any brush or debris left behind. We kindly ask for the public's patience during this process—everything will be cleaned up as the work progresses.
On the utilities front, Salem is also making major strides in infrastructure. Construction is well underway on a new municipal well, a critical investment in the long-term sustainability of our water system. Once completed, the city will begin erecting a new 400,000-gallon water tower—an essential asset that will boost capacity and reliability for homes and businesses throughout Salem. The municipal well and water tower are an ARPA grant funded project with approximately $4,600,000 in grant funding and a 10% local funding match of $47,000.
The city also recently completed its first full year of enhanced fire hydrant maintenance, which included painting hydrants and associated water valves. While not every hydrant in the city was touched during this cycle, plans are in place to continue this work in the next budget year. If approved, the same company—Fire Hydrant Services and Repair—will return to complete the remaining hydrants, while the city’s Water Department will continue replacing the units most in need.
At the Wastewater Treatment Plant, Phase 2A of the planned upgrades is progressing through the preconstruction phase. This $5 million project—entirely funded through an ARPA grant—includes the specification and ordering of parts and equipment, many of which have long lead times. Phase 2B, which includes approximately $3,500,000 in grant funding and $2,500,000 in bond-funded financing (as approved by voters in April 2023), is expected to go out for bid later this summer.
Recovery efforts from the November flooding are also ongoing, both at the Salem City Parks and at the Wastewater Treatment Plant. These efforts are focused on restoring facilities and infrastructure to full functionality and building greater resilience against future weather events.
Replacement of the playground fall zone tiles is currently underway. In addition, a separate contractor will soon begin converting the areas formerly filled with rubber chips into a solid surface. This upgrade will make the entire playground more accessible and help prevent floodwaters from penetrating beneath the adjacent tiles in the future.
Flood-related fencing repairs are also in progress at the ballfields in both the main City Park and at Al Brown Fields. Work continues at the Wastewater Treatment Plant as crews address ongoing repairs caused by the flooding.
Street repaving will be occurring later this month on the following streets: East Coffman, West First Street, and South Oak Street. If funds allow, this work will also include parts of South Louise and South Henderson. All streets will receive a 2" asphalt overlay. These streets were selected due to the deteriorating, honeycombed condition of the pavement. The existing asphalt will be milled prior to the placement of the new surface layer, ensuring a longer-lasting, smoother roadway.
The Airport T-Hangar Project has reached completion in this past year, with the construction of a new six-unit T-hangar. The cost of the project was $749,000, of which $703,000 has been reimbursed through grant funding to date. The required matching funds of approximately 5%—roughly $41,000—plus an additional $5,000 for underground electrical work were covered through the Airport Fund. These funds were accumulated from prior years' hangar rentals and airport fuel sales. While the final figures will be confirmed upon project closeout with MoDOT, no significant changes to these totals are expected.
The Salem Police Department is proud to announce that Lieutenant Counts has recently graduated from the Missouri Police Chiefs’ Command College. This program required an exceptional level of dedication, time, and effort—including time away from family—and we are grateful for his commitment to furthering his education for the benefit of the department and the community. The Command College provides high-level training for law enforcement supervisors and offers students the opportunity to earn a master’s degree. Please join us in congratulating Lt. Counts on this impressive accomplishment!
These projects and achievements represent more than just bricks and mortar—they’re part of a shared vision to strengthen Salem for the generations to come. With each improvement, we’re building a community that is not only more resilient and efficient, but also more welcoming and connected.
Stay tuned for updates as these projects continue to unfold and watch for additional projects in future months. The best is yet to come!