The following is a list of general highway maintenance and construction work planned in the mid–Missouri area Sept. 15 – 21. Weather conditions may postpone scheduled work. Many projects will include lane closures which could cause delays.
Other moving operations such as pothole patching, mowing, and pavement repairs continue in various locations. Motorists should travel with care and be alert for slow-moving equipment.
All work is weather permitting, and schedules are subject to change.
Route 8 – Culvert replacement planned Sept. 15 – 18 in various locations. One lane will remain open, and crews will flag traffic through the work zone.
Routes B, K, and N – Culvert replacement planned Sept. 15 – 18. One lane will remain open, and crews will flag traffic through the work zone.
I-44 – Bridge rehabilitation continues over Little Piney Creek. Work will require temporary daily closures. The project is scheduled for completion in September 2025.
Route J – Roadside work planned Sept. 15 – 18. One lane will remain open, and crews will flag traffic through the work zone.
North Outer Road 44 – Roadside work planned Sept. 15 – 18 from Route V to Route 8. One lane will remain open, and crews will flag traffic through the work zone.
U.S. Route 63 – Pavement improvements continue approximately one mile south of Route W. Work is being done by Courtney Construction Company under a MoDOT-issued permit. One lane will remain open with an 11-foot width restriction in place. The project is scheduled for completion in September 2025.
Route D – Bridge rehabilitation continues over I–44, approximately 7 miles southwest of Doolittle. The bridge is CLOSED, with a signed detour in place. The project is scheduled for completion in October 2025.
Missouri Route 72 and Route KK – Pedestrian facility upgrades continue on Route 72 in Rolla and Route KK in St. James. Work will require temporary closures of pedestrian facilities and intermittent single-lane closures with flaggers to direct motorists through the work zone. The project is scheduled for completion in November 2025.
Missouri Route 133 – Culvert replacements planned Sept. 15 – 18 from the city limits of Crocker to Route T. One lane will remain open, and crews will flag traffic through the work zone.
Missouri Route 28 –Bridge rehabilitation continues over I–44 in St. Robert. The bridge is CLOSED, with a signed detour in place. The project is scheduled for completion in October 2025.